Use the following project plan to start your work [mpp]
Define rates
- Architect: Standard: 800 Overtime: 1200
- Owner: Standard: 0 Overtime: 0
- Designer: Standard: 600 Overtime: 800
- Team A: Standard: 2500 Overtime: 4000
- Team B: Standard: 2500 Overtime: 4000
Progress the work
- Save plan as a baseline
- Change the progress to get the following result [jpg]
Use the following project plan to start your work [mpp]
- Analyse the earned value
- How much we spent more/less than the budget
- what tasks will require (required) more than estimated
- what task will require (required) less than estimated